Six weeks is realistic. We say that in every first phone call, and every year a handful of people tell us another builder quoted them six months. Both numbers are true — the difference is not the pool, it is how the build is run.
This is the timeline we actually hit on a standard install, with the durations for each step and the two places where projects genuinely blow out.
Week zero: the quote and the site visit
Everything starts with a visit to your block. We measure access, look at slope and soil, and talk about how your family will use the water. You get a fixed price in writing within a few days — shell, site works, fencing and handover, with no provisional sums.
“The person who quotes your pool is the person who builds it. That single rule removes most delays before they exist.”
Weeks one to three: approvals and paperwork
While you choose a colour, we lodge the approvals. In the ACT this is the step that punishes inexperience — fencing rules, boundary setbacks and utilities checks all have their own clocks. Because we lodge these every week, ours run in parallel, not in sequence.
- Building approval and plan lodgement
- Fencing compliance and boundary checks
- Dial-before-you-dig and utilities clearances
Week four: excavation and delivery
The dig itself takes a day, two on rock. The shell arrives on a truck the same week, is craned into the hole, levelled, plumbed and backfilled. This is the week the backyard looks the worst and moves the fastest.

Weeks five and six: paving, fencing, handover
Coping and paving go down, the fence goes up and passes inspection, and the pool is filled and balanced. Handover is a morning: equipment walkthrough, care routine, warranty paperwork — then it is yours.
Where timelines actually blow out
Two places. Access — a crane over the house adds cost but not time, while hand-dig access adds weeks. And decision lag — every week spent choosing a colour after approval is a week added to the calendar. Decide early and the six weeks holds.